Quality with Frans
← Site Brief
Code Watch

ACI 318-25: what the new concrete code changes for site teams

By Frans, QA/QC Manager · 28 October 2026 · 5 min read
In shortACI 318-25, the new edition of the American structural concrete code, was released at the end of January 2025 and is expected to be adopted by the 2027 International Building Code. Most changes are for designers, but a few land directly on site: hooked and headed bar development lengths, drilled-in (post-installed) rebar, and some detailing rules.

Many projects in the Gulf, Asia and Africa specify ACI 318, so a new edition matters even if you never open the code yourself. The important question on site is simple: which edition was the project designed to? Your drawings and specification answer that, and the inspection has to follow them.

The changes that reach the site

1. Hooked bars. The committee went back to the hooked-bar development length equation of ACI 318-14 and added a new modifier for bar size, because the 2019 equation did not fit the test data well for the largest bars. Hook tails on new shop drawings may differ from what your team is used to. Inspect what the approved drawing says, not what "we always do".

2. Headed bars. The 2019 equation was adjusted, giving slightly shorter development lengths. Headed deformed stirrups are now also covered, with their own detailing rules.

3. Post-installed (drilled-in) reinforcing bars. Systems for rebar drilled and bonded into existing concrete must now be qualified to a dedicated ACI qualification standard (ACI CODE-355.5). This is the change site QA/QC teams should notice most: dowels into existing slabs and walls are common, and they are only as good as the product, the installer and the hole cleaning.

4. One-way shear. A lower limit was added to the concrete's contribution to shear strength. Retaining walls, basement walls, pile caps on closely spaced piles and rigid footings go back to the older ACI 318-14 equations. That is design work, but it can change the reinforcement you see on the drawings.

5. Structural integrity and deep foundations. Perimeter beam detailing was improved to reduce the risk of progressive collapse if a perimeter column is lost, and the deep foundation rules were expanded and made consistent.

6. Two new optional appendices: one on sustainable design and construction (a framework, with no fixed carbon limits) and one on performance-based wind design.

Check on your site tomorrow

  1. Find the ACI 318 edition named in your specification and design basis report. Make sure your ITPs and checklists follow that edition.
  2. For any drilled-in dowels: approved product, installer trained or certified for that system, hole depth and diameter checked, holes cleaned exactly as the manufacturer requires, and the inspection recorded before the adhesive is injected.
  3. Check hook and headed-bar details against the approved shop drawings, especially on large bars.
  4. If the design moves to ACI 318-25 mid-project, ask the engineer for revised drawings rather than marking up old ones on site.

ACI 318-19 vs ACI 318-25 at a glance

TopicACI 318-19ACI 318-25
Hooked barsNew development length equation introduced in 2019Back to the ACI 318-14 equation, with a new bar-size modifier
Headed bars2019 equationEquation adjusted: slightly shorter lengths; headed deformed stirrups added
Post-installed rebarLimited provisionsSystems must be qualified to ACI CODE-355.5
One-way shear2019 equationsLower bound on the concrete contribution; some walls, pile caps and rigid footings back to ACI 318-14 equations
Structural integrityExisting perimeter beam rulesImproved detailing based on new test data
Deep foundationsSpread across provisionsExpanded and unified for all seismic design categories
SustainabilityNot coveredNew voluntary appendix (no fixed carbon limits)
WindNot coveredNew optional appendix for performance-based wind design
Building codeThe edition most current codes refer toExpected in the 2027 International Building Code
Free: Rebar inspection checklist
The 31-point checklist I use before every concrete pour, including laps, anchorage and cover.
Download the checklist

Sources: Informed Infrastructure: ACI CODE-318-25 updates · ICC / S.K. Ghosh: significant changes in ACI 318-25. Plain-language summary; your project's specified code edition and the engineer's design apply.

WhatsApp